1.每次裝料前用水沖洗進料口,使進料口在裝料時保持濕潤。
1. Wash the feed port with water before each loading to keep the feed port wet during loading.
2.在裝料的同時向隨車自帶的清洗用水水箱中注滿水。
2. Fill the cleaning water tank with water while loading.
3.裝料后沖洗進料口,洗凈進料口附近殘留的混凝土。
3. After loading, wash the inlet and clean the residual concrete near the inlet.
4.到工地卸料后,沖洗出料槽,然后向混凝土貯罐內加清洗用水30—40 L;在車輛回程時保持混凝土貯罐正向慢速轉動。
4. After unloading at the construction site, wash the discharge tank, and then add 30-40 l of cleaning water to the concrete storage tank; Keep the concrete storage tank rotating forward and slowly when the vehicle returns.
5.下次裝料前切記放掉混凝土貯罐內的污水。
5. Remember to drain the sewage in the concrete storage tank before the next loading.
6.每天收工時徹底清洗混凝土貯罐及進出料口周圍自動,怎么保養自動上料攪拌車保證不粘有水泥及混凝土結塊。
6. At the end of each day, thoroughly clean the concrete storage tank and around the inlet and outlet. How to maintain the automatic feeding mixer to ensure that there is no cement and concrete caking.
7、隨車帶上減水劑:減水劑是一種在維持混凝土坍落度不變的條件下,能減少拌合用水量的混凝土外加劑,隨車攜帶,能對混凝土進行很好的調節。

7. Carry water reducing agent with the vehicle: water reducing agent is a concrete admixture that can reduce the mixing water volume under the condition of maintaining the same concrete slump. It is carried with the vehicle and can well adjust the concrete.
8、回廠檢查罐內水量:每次出車任務完成回到站內的時候,檢查儲水罐內的水量,讓水罐中的水隨時處于滿罐的狀態,以備不時之需。
8. Return to the factory to check the water volume in the tank: when returning to the station after completing the driving task, check the water volume in the water storage tank to keep the water in the tank full at any time for emergency needs.
9、離廠前檢查混凝土質量:可能會因為原料的不同,每一盤混凝土質量都會有變化。
9. Check the concrete quality before leaving the factory: the quality of each plate of concrete may change due to different raw materials.
10、減少車輛行駛時間:混凝土運距一般在直徑30千米范圍以內,出車之前規劃好路線以及車輛通行情況。
10. Reduce vehicle travel time: the concrete transportation distance is generally within 30 km in diameter, and the route and vehicle traffic shall be planned before departure.
11、減少損失先卸料:如果遇到人為因素或者不可抗因素,導致長時間無法卸料的情況,一旦發現混凝土開始凝結,在報備負責人之后立刻進行卸料,以防整個罐體報廢。
11. Unloading first to reduce losses: if it is impossible to unload for a long time due to human factors or irresistible factors, once it is found that the concrete begins to set, it shall be unloaded immediately after reporting to the person in charge to prevent the whole tank from being scrapped.